Recovery of Subcontract Payments and Release of Bank Guarantees Under a SAR 1 Million Contract

SAR 1,000,000

Disputes arising from subcontracting arrangements require careful review of contracts, completed works, payment certificates, and bank guarantees.In this matter, Atyar Advocates and Legal Consultants represented a private contracting company in a financial claim of approximately SAR 1 million after the counterparty failed to pay outstanding amounts and release the bank guarantees despite completion of the agreed works.The legal team established completion of the works, proved the client’s entitlement, and secured an order for payment of the outstanding amounts and return of the bank guarantee. After approximately two and a half years, the judgment was upheld by the Court of Appeal and fully enforced, resulting in recovery of the awarded amounts for the client.

Quick Matter Overview

Contract Value

Approximately SAR 1,000,000

Nature of the Contract

Subcontract

Subject of the Claim

Outstanding payments and bank guarantees

Duration of the Matter

Approximately two and a half years

Judicial Route

Commercial Court, Court of Appeal, and Enforcement Court

Outcome

Favourable Judgment & Full Recovery

Background of the Ownership Matter

The dispute arose from a subcontract worth approximately SAR 1 million, where the client completed the works but the counterparty failed to pay the outstanding amounts or release the bank guarantees. Atyar Advocates and Legal Consultants pursued a financial claim, supported by project records, payment certificates, and financial documents.After approximately five hearings, the court ruled fully in the client’s favour, ordering payment of the outstanding amounts and return of the bank guarantee. The judgment was upheld on appeal, and enforcement proceedings resulted in full recovery of the awarded amounts.

A professional scene combining legal and architectural elements with an urban view, symbolizing a construction dispute and the recovery of financial rights within a contractual framework.

Contract Value

Approximately SAR 1 million

Nature of the Works

Subcontracting works

Subject of the Dispute

Non-payment and withheld bank guarantee

Key Evidentiary Issue

Payment Certificates & Main Contractor Approval

Nature of the Contractual Dispute

The dispute centred on payment rights arising from performance of a subcontract, together with the counterparty’s failure to release the bank guarantees connected with the contract.

The principal matters addressed included:

Essential Elements of the Dispute

Subcontract

Reviewing the contractual obligations governing the relationship and identifying each party’s rights and responsibilities.

Completed Works

Establishing that the client performed the works required under the subcontract, forming the basis of the financial claim.

Payment Certificates

Reviewing the payment certificates and related documents and connecting them to the amounts claimed.

Bank Guarantee

Assessing the contractual and legal basis for seeking release and return of the bank guarantee.

Outstanding Payments

Establishing the sums due as a result of the completed works and the counterparty’s failure to pay.

Enforcement of the Judgment

Following the judgment through enforcement until the bank guarantee was returned and the awarded amounts were recovered in full.

Key Legal Challenges

Proving Completion of the Subcontract Works

It was necessary to establish that the client had performed the works required under the subcontract. This formed the principal basis for claiming both the outstanding payments and the related contractual rights.

Dispute Over the Payment Certificates

The counterparty denied that the main contractor had approved the relevant payment certificates, requiring detailed review and presentation of the available documents and factual circumstances.

Recovery of the Bank Guarantee

The dispute concerned not only unpaid financial entitlements but also a bank guarantee that remained unreleased after completion of the works. It was therefore necessary to establish the legal and contractual basis for its return.

Establishing the Full Financial Entitlement

The completed works, payment certificates, and amounts claimed had to be linked clearly before the Commercial Court.

Multiple Debts Against the Judgment Debtor

The enforcement stage was complicated by multiple outstanding debts against the judgment debtor, creating additional difficulty in recovering the awarded sums.

Achieving Full Recovery

The final challenge was converting the successful judgment into actual recovery. Enforcement continued until all awarded amounts were recovered and delivered to the client.

Our Legal Strategy

eviewing the Contract and Supporting Documents

The engagement began with review of the subcontract, payment certificates, project documents, and materials relating to the bank guarantee.

Establishing Completion of the Works

The available facts and evidence were organised to demonstrate that the client had completed the agreed works.

Addressing the Payment Certificate Dispute

A legal and evidentiary response was prepared to address the counterparty’s denial regarding the main contractor’s approval of the payment certificates.

Building the Financial Claim

The subcontract, completed works, payment certificates, bank guarantees, and outstanding amounts were integrated into a structured claim before the Commercial Court.

Managing the Litigation and Appeal

The matter was litigated until judgment was obtained in full, and the judgment was then defended before the Court of Appeal until it was upheld.

Enforcement and Recovery

Enforcement was pursued despite the judgment debtor’s multiple outstanding liabilities until the full rights and amounts awarded were recovered and delivered to the client.

Legal Services Provided

Legal Advice

Providing advice concerning the subcontract, outstanding payments, bank guarantees, and the appropriate legal route for recovery.

Comprehensive Legal Study

Reviewing the subcontract, payment certificates, facts, supporting documents, and the client’s legal position.

Litigation

Managing the claim and representing the client in establishing entitlement to the disputed payments and bank guarantee.

Representation Before Authorities

Representing the client throughout the judicial and enforcement stages of the matter.

Drafting Legal Memoranda

Preparing the legal memoranda and responses required to support the client’s case.

Drafting Pleadings

Preparing the statement of claim, objections, and other submissions required throughout the proceedings.

Legal Insight

In subcontracting disputes, entitlement to payment is closely connected to evidence of completed works and the documentation recording project progress and payment certification.The matter becomes more complex where outstanding payments are combined with continued retention of  bank guarantees* after the works have been completed.A favourable judgment is also not the practical end of a dispute unless enforcement is pursued until the amounts and guarantees awarded by the court are actually recovered.

Legal Value Delivered to the Client

The Firm’s Experience in Construction Disputes and Bank Guarantees

Atyar Advocates and Legal Consultants provides legal services in construction disputes, subcontracting matters, and financial claims arising from project execution.The firm’s services include reviewing contracts, payment certificates, and bank guarantees, assessing completion of works and entitlement to payment, and preparing claims, pleadings, and legal memoranda.The firm also represents clients before the Commercial Courts, manages matters through the appellate stage, and pursues enforcement until the financial rights awarded by the court are recovered.

Legal Team Responsible for This Matter

Dr. Turki altayyar

Prof. Dr. Turki Al-Tayyar

Founder and Managing Partner, and an expert in the judiciary, legal practice, arbitration, and university education, with more than 25 years of combined experience.

Mr. Salem Saad Al-Dosari

Partner specialising in administrative contracts, investment, and litigation, with extensive experience in administrative and commercial cases.

Practice Areas Related to This Matter

Need Legal Support to Recover Subcontract Payments or Bank Guarantees?

If your company has completed subcontract works but has not received its outstanding payments or the relevant bank guarantees have not been released, Atyar Advocates and Legal Consultants  provides legal advice, legal study, litigation, drafting, appellate representation, and judgment enforcement services throughout Saudi Arabia.

جاهز لحماية حقوقك أو تطوير أعمالك؟

تواصل معنا اليوم واحصل على استشارة قانونية موثوقة

سواء كنت فردًا تبحث عن تمثيل قانوني موثوق أو شركة تحتاج إلى دعم قانوني متخصص، نحن في شركة أطيار للمحاماة والاستشارات القانونية جاهزون لمساعدتك. دعنا نكون شريكك القانوني في كل خطوة، بخبرة تتجاوز 23 عامًا في الأنظمة السعودية.

شركة الطيار للمحاماة والاستشارات القانونية

بيانات الاتصال

مجالات الممارسة

القانون التجاري والشركات

صياغة العقود والوثائق القانونية

القانون المالي والمصرفي

الضرائب والزكاة والجمارك

العقارات والملكية الخاصة

تابعنا

النشرة الإخبارية

You have been successfully Subscribed! Ops! Something went wrong, please try again.

© 2025 All Right Reserved Al Tayyar Leagal company